Mammoet was trusted with this float in project by MCE GmbH, a company of the HABAU GROUP. The task was to move the two main supporting structures of the new bridge – each weighing around 2,800t, 100m long and 32m wide – from the pre-assembly area on the side of the Danube to the piers in the middle of the river.

As the over 100-year-old railway bridge crossing the Danube in Linz, Austria could not be reconstructed, it was decided that a new combined road and railway bridge would be built. Weighing 8,400t (pure steel weight of the supporting structure), this would be one of the heaviest bridges installed in Austria in recent years.

Early in the planning phase, a tight schedule was drawn up in cooperation with the customer to minimize disruptions and interruptions to shipping traffic on the highly-frequented waterway. The engineering concept was to use Mammoet’s Mega Jack 800 for the jacking of the two bridge segments. This system was capable of raising the 2,800t bridge segments from their pre-assembly height to the float-in height quickly and safely.

During the preparatory engineering phase, Mammoet’s team received the information that the two steel structures would be heavier than first planned, due to necessary additional strengthening measures. Thus, the original engineering concept had to be adapted as quickly as possible without jeopardizing the project’s tight schedule.

Mammoet’s engineers planned to move the bridge sections from their point of the assembly via SPMTs, driving them onto barges, which would then be accurately positioned above the bridge foundations for installation to take place. The water level always had to be monitored, as high or low water would have meant delays in the schedule.

Due to precise planning and excellent cooperation, both bridge segments were safely floated in and installed, and the Danube could be re-opened ahead of schedule several times. The bridge is expected to be completed in October 2021 and, as a key project, will greatly relieve urban traffic in Linz in the future.

Read more details regarding this project: https://breakbulk.news/video-mammoet-floats-in-new-danube-bridge-in-linz-austria/

info@projectfreight.net

Share
Published by
info@projectfreight.net

Recent Posts

Maritime News: Current Trends and Future Projections

In the ever-fluctuating world of maritime freight and logistics, recent trends and future projections paint…

5 days ago

Unraveling the Distinctions: House Bill of Lading vs. Master Bill of Lading

Unraveling the complexities of shipping documentation: Discover the divergences between House Bill of Lading and…

2 weeks ago

Returning to a Subject that has been Covered: The Importance of Verified Gross Mass in Maritime Shipping

Returning to a subject that has been covered not infrequently in this newsletter, the issue…

4 weeks ago

Challenges and Solutions in Decarbonizing the Global Logistics Industry

The global logistics and transport sector is grappling with monumental challenges as it strives to…

4 weeks ago

Green Logistics: Balancing Ecology and Economy

Eco-logistics or green logistics, as it is commonly referred to, has emerged as a pivotal…

2 months ago

Innovations Reshaping Breakbulk Shipping For The Better

Breakbulk cargo, also referred to as non-containerized or project cargo, is undergoing a transformative phase…

2 months ago